Duke Energy wants to build a new gas plant. Regulators said not so fast.
Why it’s here: This is a state utility regulatory ruling on a gas plant tied to data center demand and references the White House Ratepayer Protection Pledge, giving it a federal policy hook, though the decision itself is state-level.
Trace across the boardItem
Sep 21Canary MediaDuke Energy wants to build a new gas plant. Regulators said not so fast.North Carolina regulators rejected Duke Energy's permit to build a 255-MW gas plant in Richmond County, estimated at $584 million.1 outletEnergy1 linked
Connected
1 links- NewsRegulators approve Duke Energy’s rate increase, set rules for data centersBoth involve Duke Energy